SINERGI Vol. No. October 2025: 857-865 http://publikasi. id/index. php/sinergi http://doi. org/10. 22441/sinergi. Experimental investigation of the Moment Bolted Coupler (MBT) with steel on the bond strength under different monotonic pull-out tests Mohamad Amir Mohamad Nor. Nursafarina Ahmad*. Hazrina Mansor Faculty of Civil Engineering. Universiti Teknologi MARA (UiTM). Shah Alam. Malaysia Abstract The bond strength between steel reinforcement bars and mechanical bolted couplers (MBT) is essential for the structural integrity of reinforced concrete structures. However, various pull-out test methods yield inconsistent results when assessing this bond This research examines the impact of reinforcement bar diameter . mm, 16mm, and 20m. and three different pull-out test configurations (M1. M2, and M. on the bond strength of MBT The M2 method, employing direct tensile loading and a short clamp zone, consistently produced the highest bond strength values across all bar diameters. Its simplicity, reliability, and adherence to standardized procedures make it the preferred method for determining the maximum bond capacity of MBTs. While the M1 and M3 methods offer insights into coupler behavior under complex loading scenarios, they exhibit lower bond strength values compared to M1. The M2 pull-out test method is recommended as the primary method for evaluating the bond strength of MBT in practical applications, with M3 testing as a potential supplement for a more comprehensive understanding of coupler behavior. Keywords: Bond Strength. Failure mode. Maximum load capacity. Mechanical Bolted Coupler. Pull Out Test. Article History: Received: October 17, 2024 Revised: March 24, 2025 Accepted: July 29, 2025 Published: September 5, 2025 Corresponding Author: Nursafarina Ahmad Faculty of Civil Engineering. Universiti Teknologi MARA (UiTM). Shah Alam. Malaysia Email: nursafarina1131@uitm. This is an open-access article under the CC BY-SA license. INTRODUCTION Steel is a fundamental material in modern construction due to its strength, durability, and Steel connections, including bolted, welded, and mechanical splice connections, are crucial for ensuring the stability and safety of the steel structure. Mechanical splice connections, such as couplers, provide huge advantages in terms of ease of assembly and design flexibility. Couplers are clearly advantageous over traditional lap splicing, as it can directly transfer loads between reinforced bars and reduce steel consumption, thus minimizing congestion at joints . Mechanical couplers are commonly used in construction as an alternative to the traditional lap splicing method. Mechanical couplers offer significant advantages, particularly in term of cost reduction for reinforcement bars and fabrication expenses, as well as reduced congestion at joints. The concept of connection for mechanical couplers typically involves a threaded annual sleeve that fits the bar at the junction, connecting a different rebar in the sleeve region using grout or a screw as a connector. There are various types of mechanical couplers available nowadays with specific applications and characteristics. Hybrid couplers, for instance, incorporate two distinct connection mechanisms, while transition couplers are designed to connect reinforcement bars of different diameters. For shear screw couplers, utilize screws designed to break at a predetermined torque, enabling controlled separation under shear stress . Grouted couplers enhance structural stability by filing the Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A SINERGI Vol. No. October 2025: 857-865 steel sleeve with cementitious material, providing a robust connection for reinforcing bars . Threaded couplers are well-known for their exceptional structural performance in concrete structures, enhancing load-bearing capacity and ductility . On the upside, the mechanical coupler offers abundant benefits, but it is essential to consider the downsides and potential limitations. For instance, the bond strength between the coupler and the rebar can be influenced by factors such as the cleanliness of the rebar surface . the presence of rib. , as well as the presence of contaminants . Additionally, steel diameter can significantly affect bond strength as well as bond failure . A large diameter can increase the likelihood of bond failure. This failure can manifest as either slippage failure, where the steel reinforcement slides within the concrete, or pullout failure, where the steel reinforcement bar is completely extracted from the concrete. Excessive slippage between the coupler and the reinforcement bar under dynamic or static loading indicates poor coupling efficiency and can be affected by a few factors, for example, thread pitch, thread angle, bar diameter, and temperature . Understanding these limitations is crucial for ensuring the proper selection, design, and installation of mechanical couplers to ensure the structural integrity and long-term performance of RC structures. Ensuring the reliability and environmental scenarios and dynamic loading, is quite challenging in construction projects. An earthquake event can induce vibrations in structures, potentially causing slippage failure between couplers and reinforcement bars. reinforced concrete (RC) structures, the continuity of reinforcement in the inelastic zone is crucial for maintaining structural integrity under high dynamic loads like earthquakes. Traditional lap splicing may lead to over-reinforcement and non-ductile behavior due to stress concentration at the lap ends, inadvertently altering the deformation capacity of the reinforced structure . The vital challenge to comprehending the reliability and efficiency of mechanical couplers is to understand their bond behavior in terms of bond Experimental configuration setups for evaluating the bond strength of mechanical couplers have been plagued by inconsistencies and significant variation in results, such as bond strength and failure, depending on the test setup . The methodologies, including the uniform pullout test (UPT) . , direct pullout test (DPT) . , and direct tension pullout test (DTPT) . have led to diverse and often conflicting results. Therefore, a comprehensive investigation is needed to determine the most suitable testing method for accurately and reliably determining the bond strength. This research aims to address this issue by systematically evaluating the various pullout test setups to identify the appropriate method for determining the bond strength of the MBT mechanical coupler. METHODS Pullout testing is a fundamental method for evaluating the bond behavior between the concrete and steel reinforcement. This test provides crucial insight into the structural integrity of the reinforced concrete member. The effectiveness of the pullout test method depends on its simplicity, cost-effectiveness, and ability to systematically control and vary the parameters, making it able to assess coupler connection effectiveness and bond strength under tensile stress . Pull-Out Test Method conducted utilizing three different pull-out test configurations, which are: uniform pullout test (UPT), direct pullout test (DPT), and direct tension pullout test (DTPT). The UPT was represented as Method 1 (M. DPT was Method 2 (M. , and DTPT was Method 3 (M. The upper adjustable crosshead of the Universal Testing Machine (UTM-1. was used to securely clamp the upper end of the reinforcement bar, and the lower crosshead firmly held the upper portion of the coupler for the setup M1 test. The pulling force was applied through the upper crosshead, as illustrated in Figure 1. Method 1 was clamping the top reinforcement bar using the upper movable crosshead of the Universal Testing Machine (UTM), while the lower crosshead secured the top head of the coupler using a steel plate. This configuration subjected the coupler to a uniform tensile force, simulating a situation where the load is primarily transferred through the upper coupler The clamp point for method 1 was located at a distance of 8db . iameter ba. from the top head of the coupler. The requirement was suggested based on American Society for Testing and Materials (ASTM) E8 . Then, for the M2 test setup, the upper movable crosshead clamped the upper reinforcement bar at 2db . iameter ba. The bottom of the MBT coupler is grasped by the lower movable crosshead, as shown in Figure 2. Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A p-ISSN: 1410-2331 e-ISSN: 2460-1217 Method 2 introduced a loading condition by clamping the top reinforcement bar at 2db and clamping the bottom of the coupler. This method simulates the short region condition by transferring the tensile force at the rigid region of the mechanical coupler . Meanwhile, for the M3 test setup configuration, the UTM grips clamped both ends of the reinforcement bar at 2db from both coupler The pulling force will be applied to the upper grip as shown in Figure 3. This configuration subjected the coupler to the purely tensile load, potentially influencing the failure mode and the ultimate load resistance of the mechanical coupler connection . Details of the specimen A comparative pullout test for the Moment Bolted Coupler (MBT) was carried out on three different configuration setups. The schematic diagram of the MBT is shown in Figure 4, and the detailed specimen of the pullout test is shown in Table 1. Figure 4. configuration of the Moment Bolted Coupler (MBT). Actual MBT Figure 1. M1 setup . Schematic drawing. Experimental testing Figure 2. M2 setup . Schematic drawing. Experimental testing Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A SINERGI Vol. No. October 2025: 857-865 Figure 3. M3 setup . Schematic drawing. Experimental testing In this research, pullout test specimens were prepared based on two different parameters, which are bar diameters . mm, 16 mm, and 20 m. and pull-out setup configuration (Method 1. Method 2, and Method . The specimens were named as M1-MBT12 . s depicted in Figure . , where M1 indicates a type of pull-out method. MBT12 indicates a diameter bar. A total of nine specimens for all tests were prepared. The specimen dimensions in this study are measured as 600 mm in length for the upper reinforcement, and the bottom reinforcement measures 300 mm in length, as shown in Figure 6. In compliance with ASTM E8, a pullout force was applied to each specimen at a loading rate of 0. 5 mm/min . linear variable differential transformer (LVDT) was used to measure the specimen displacement during the pullout test. According to the configuration setup, the LVDTs were positioned at the end of the steel plate that was fastened to the upper reinforcement. Two strain gauges were affixed longitudinally along the bar deformation, as depicted in Figure 6. Figure 5. Notation type of specimen Figure 6. Pull-out specimen dimension Table 1. Details of the pullout specification Specimen Rebar . Pull-out test Coupler length. L . External diameter, d . No. of Bolts Clamp zone M1-MBT12 M2-MBT12 M3-MBT12 M1-MBT16 M2-MBT16 M3-MBT16 M1-MBT20 M2-MBT20 M3-MBT20 Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A p-ISSN: 1410-2331 e-ISSN: 2460-1217 RESULTS AND DISCUSSION Based on this study, the bond strength is the force required to pull a steel bar out of the coupler sleeve. The bond strength . was determined by calculating the ultimate axial tensile force (F) in kN, the nominal bar diameter. , and the embedded length (L. The embedded length refers to the insertion of steel for each coupler in mechanical couplers. Table 2 shows the value of the bond strength for the testing specimen. The bond strength . is calculated using . yua = ya/. uUyccyca yayce ) The bond strength-displacement curve shows the relationships of MBT to the three different pullout test configurations (M1. M2, and M. Figure 7 shows the bond strengthdisplacement curve for all specimens. The pullout testing method significantly affects the behavior of the bond strength-displacement curve. The M2 setup shows the highest bond strength, which is 14MPa for 12 mm, 32. 48MPa for 16mm, and 27MPa for 20 mm. This suggested that the load Figure 7. Bond strength Ae displacement curve transfer within a short region in M2 increases the bond strength compared to direct tension on M1. The curves for M2 and M3 are more gradual, replicating steel stress-strain behavior, indicating the ductile failure mode, which is steel rupture. The M1 curve shows the rapid drop, suggesting brittle failure, which is steel slippage. M2 and M3 setups typically fail at higher displacement compared to the M1, which indicates that M2 and M3 are more ductile compared to M1. Table 2. Bond strength of the specimens Specimen M1-MBT12 M2-MBT12 M3-MBT12 M1-MBT16 M2-MBT16 M3-MBT16 M1-MBT20 M2-MBT20 M3-MBT20 Embedded length. Le . Ultimate Tensile Force. F . N) Ultimate Bond Strength (MP. Maximum displacement . Figure 8. Bond strength-displacement relationships on different diameters. 20mm Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A SINERGI Vol. No. October 2025: 857-865 Initially. Figure 8 shows that all methods exhibit a linear increase in bond strength with increasing displacement, indicative of an elastic Beyond this elastic limit, the specimens diverge in behaviour based on the setup. For M1MBT12. M2-MBT12, and M3-MBT12, the failure mode is steel fracture. The plastic limit bond strength ranges from 22. 18 MPa to 24. MPa, the plastic limit displacement varies 55 mm and 11. 45 mm, the rupture bond strength falls within 12. 73 MPa to 20. MPa, and the break point displacement spans 39 mm to 38. 27 mm. The ultimate displacement and bond strength for this group are 45 mm to 35. 62 mm and 26. 40 MPa to 28. MPa, respectively. Similarly. M1-MBT16. M2-MBT16, and M3MBT16 also exhibit steel fracture. Their plastic limit bond strength varies from 25. 80 MPa to 26. MPa, plastic limit displacement ranges from 8. mm to 16. 68 mm, rupture bond strength is 23 MPa and 22. 61 MPa, and break point displacement falls within 30. 53 mm to 49. The ultimate displacement and bond strength for this group are 22. 11 mm to 41. 54 mm and 58 MPa to 32. 48 MPa, respectively. In the case of M1-MBT20, the failure mode is slippage, whereas M2-MBT20 and M3-MBT20 experience steel fracture. The plastic limit bond strength for M1-MBT20 is 30. 16 MPa, the plastic limit displacement is 11. 78 mm, the rupture bond strength is 20. 43 MPa, and the break point displacement is 31. 03 mm. The ultimate displacement and bond strength for M1-MBT20 61 mm and 33. 46 MPa, respectively. For M2-MBT20 and M3-MBT20, the plastic limit bond strength ranges from 29. 44 MPa to 05 MPa, the plastic limit displacement is 07 mm and 24. 28 mm, rupture bond strength varies from 18. 37 MPa to 26. 06 MPa, and break point displacement falls within 41. 60 mm to 23 mm. Their ultimate displacement and bond strength are 31. 91 mm to 45. 36 mm and 34. MPa to 37. 27 MPa, respectively. Figure 9. Influences of bar diameter on bond shows the highest bond strength, 30. 14MPa, 48MPa and 37. 27MPa for all different diameters when compared to M1 and M3. The percentage difference was 12. 40% for M1, 2. for M2, and 10. 22% for M3 for diameters 12, 16 and 20 mm, respectively. It can be seen in Figure 9 that M3 exhibit higher bond strength when compared to M1 for diameters 12 mm and 20 mm. However, the bond strength for M1 diameter 16 mm is slightly higher, 45% compared to M3 diameter 16 mm. Based on three different setup methods, it shows that the M2 setup emerges as the most significant configuration for maximizing bond strength across different bar diameters. However, the bond strength relationship between the pull-out setup method can be concluded as a dependent Failure mode Table 3 shows the failure mode of the MBT during the pull-out test. Steel bar rupture failure is the most notable observation for the failure mode that appears for all setup methods. However, only steel bar slippage failure occurs on specimen M1MBT20. Effect of the bar diameter The relationship between the bond strength and bar diameter in pull-out is illustrated in Figure Based on the results, the diameter bar has a significant effect on increasing the bond strength when the diameter of the rebar increases for all method setups Thus, it influences the ductility and load-carrying capacity of the mechanical coupler. The M2 pull-out method Figure 10. Steel bar slippage failure Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A p-ISSN: 1410-2331 e-ISSN: 2460-1217 Figure 10 shows the steel bar slippage occurring on the M1-MBT20 due to the rupture of the bolts. Each bolt was designed to carry a portion of the tensile force to the coupler When one of the bolts breaks or ruptures . s shown in Figure . , the load previously carried by the failed bolt is immediately transferred to the remaining bolt. This sudden increase in the load exceeded their design capacity, leading to the steel barAos slippage failure. Steel rupture failure occurs when the applied load exceeds the yield strength of the reinforcing steel bars, causing the steel to rupture, as illustrated in Figure 12. This indicates that the MBT coupler has functioned appropriately, thus reinforcing bars achieved the maximum strength Previous researchers . have also observed that most failure modes are steel bar ruptures that occur when the applied load exceed the tensile strength of the steel. According to Alharbi et al. , steel bar slippage occurs when the load transfer between the shear screw coupler and the rebar has deteriorated. According to Khedmatgozar . , steel bar slippage occurs when the load transfer between the shear screw coupler and the rebar has deteriorated. Figure 11. Rupture bolt for M1-MBT29 Figure 12. Rupture of the steel bar Shear screw couplers rely on a combination of screw penetration and shear friction to transfer load effectively. Rupture of the screw coupler leads to the degradation of the load transfer. As a result, the reinforcement bar was slip from the bottom sleeve of the mechanical coupler. CONCLUSION This research provides a comprehensive evaluation of three different pull-out test configuration methods (M1. M2. for assessing the bond strength of MBT. The conclusion can be based on the results analysis. The results demonstrate that the M2 method, characterized by direct tensile loading and a standard clamp zone, consistently yields the highest bond strength values across various bar diameters. This method's simplicity, reliability, and adherence to standardized procedures make it the most suitable choice for determining the maximum bond capacity of MBT. While M1 and M3 offer valuable insights into coupler behavior under eccentric loading and varying clamp zone positions, they exhibit lower bond strength values compared to M2. Based on the findings, it is recommended that the M2 pull-out test method be adopted as the primary method for evaluating the bond strength of MBT in practical applications. Table 3. Failure mode of the specimen Specimen Failure mode Ultimate Stress. E . Rupture bond strength, yua (MP. Break point . M1-MBT12 M2-MBT12 M3-MBT12 M1-MBT16 M2-MBT16 M3-MBT16 M1-MBT20 M2-MBT20 M3-MBT20 Steel fracture Steel fracture Steel fracture Steel fracture Steel fracture Steel fracture Slippage Steel fracture Steel fracture Nor et al. Experimental investigation of the Moment Bolted Coupler (MBT) with A SINERGI Vol. No. October 2025: 857-865 While increasing bar diameter generally enhances bond strength, the specific pull-out setup and clamp zone can significantly modulate this relationship. This method's consistency and ease of implementation make it a reliable tool for quality control and assurance in construction Limitation This study acknowledges certain limitations that should be considered when interpreting the The sample size, while sufficient for drawing preliminary conclusions, could be expanded in future research to enhance the Additionally, the study focused on a (MBT). Further research could investigate the bond behavior of other coupler types to generalize the findings Acknowledgement Special thanks to Structure Laboratory's technical staff at the Faculty of Civil Engineering. Universiti Teknologi MARA. Shah Alam. Malaysia, for assisting with instrumentation and data REFERENCES