Journal ofRenewable Renewable Energy. Electrical. Computer Engineering Journal of Energy. Electrical, and and Computer Engineering, 5 . 37-44 Volume 5. Number 1. March 2025. eISSN 2776-0049 Research Original Article DOI: https://doi. org/10. 29103/jreece. Earthquake Risk Management for Mini-Hydro Power Plant: A Case Study Approach Hafit Isandono1. Aep Saepul UyunA1,2. Andy Tirta1,2. Erkata Yandri1,2. Syukri Muhammad Nur1,2 1Graduate School of Renewable Energy. Darma Persada University. Jl. Radin Inten 2. Pondok Kelapa. East Jakarta, 13450. Indonesia 2Center of Renewable Energi Studies. Department of Renewable Energy Engineering. Darma Persada University. Jl. Radin Inten 2. Pondok Kelapa. East Jakarta, 13450. Indonesia Corresponding Author: aepsuyun@pasca. id | Phone: 6282123850197 Received: September 30, 2024 Revision: January 15, 2025 Accepted: March 10, 2025 Abstract This study evaluates the impact of an earthquake on a mini-hydropower plant (MHP) and formulates a disaster management strategy to enhance the operational resilience of MHPs against seismic events. Data was collected through interviews with relevant stakeholders, direct observations, and analysis of pertinent documents. The findings indicate that the 2018 Lombok earthquake caused severe damage to the catchment area, triggering increased sedimentation that disrupted the MHPAos operation, resulting in decreased electricity production and escalated operational costs. Mitigation measures were implemented and proved effective in reducing debris-related downtime and improving electricity generation. Thes findings are expected to provide guidance for MHP operators in mitigating the negative impacts of earthquakes and similar disasters on plant operations. Keywords: Mini-Hydropower Plant. Disaster Management. Mitigation. Earthquake. Strategy Introduction Hydropower is a renewable energy source that substantial promise for future development in Indonesia (Abdullah et al. By 2020, the nation had already established 379 hydropower plants, reaching an installed capacity of 5174 MW . this total, 375 MW was contributed by mini-hydro power plants (PT PLN (Perser. , 2. However, a significant untapped potential of 96627 MW remains, including 21125 MW attributable to mini-hydro power, distributed across 7071 locations throughout the archipelago (Pranoto et al. , 2. Mini-hydro power is categorized as a hydroelectric power plant with a capacity ranging from 1 to 10 MW (Pranoto et , 2. Interest in developing mini-hydro power plants is steadly increasing, driven by their abundant potential and more affordable investments cost compared to large-scale hydroelectric plants. Despite being a promising energy source, mini-hydro power plants exhibit vulnerability to natural disasters, including earthquakes, floods and landslides. This susceptibility to such hazard arises from several factors. Firstly, the construction of these plants often occurs in mountainous regions, which are inherently situated at tectonic plate boundaries, thus elevating the risk of seismic activity. Furthermore, mountainous areas are frequently in proximity to volcanic activity, including eruptions and volcanic earthquakes that can trigger seismic activity in surrounding areas. Secondly, the location of hydro power plants is often in riverine areas, which increases the risk of flooding. Dams, as part of these plants, also possess the potential to become sources of disaster, particularly if structural damage occurs, which could lead to flooding in downstream areas. Finally, mountainous regions tend to be characterized by fragile and fractured rock formations, coupled with slopes prone to landslides during periods of intense rainfall or seismic activity. For instance, the Kokok Putih mini-hydro power plant, constructed on the slopes of Mount Rinjani in East Lombok. West Nusa Tenggara Province, sustained substantial damage due to earthquake that struck Lombok Island in 2018. This seismic event resulted in significant structural damage to its facilities, causing severe disruption to its operational capacity. This incident underscores the critical importance of effective disaster management in ensuring the safety and operational continuity of mini-hydro power plants. The selection of the Kokok Putih mini-hydro power plant in Lombok as the focus of this research is based on several key factors. Firstly, this facility experienced significant damage from the 2018 earthquake, rendering it a pertinent case study for analyzing the vulnerability and resilience of mini-hydro power plant to seismic events. Secondly, in the aftermath of earthquake, the plant evaluated implemented various mitigation measures, the effectiveness of which can be evaluated within this study. The study aims to evaluate the impact of the earthquake on mini-hydro power plant operations, and the steps required by mini-hydro power plant managers in dealing with and managing disaster emergency situations. This case study of operational mitigation measures at the Kokok Putih mini-hydro power plant can provide valuable insight into effective earthquake mitigation strategies to be applied to similar mini-hydro power plant in earthquake-prone areas, thereby contributing to increasing the resilience of renewable energy infrastructure in Indonesia. Journal of Renewable Energy. Electrical, and Computer Engineering, 5 . 37-44 Literature Review Disaster impact management activities are primarily focused on the repair of public facilities, buildings and surrounding environment of affected areas (Nakoe & Lalu, 2. However, research on power plant infrastructure, particularly facilities utilizing renewable energy resources, remains limited. This scarcity of research is attributable to the inherent unpredictability of disasters. Nevertheless, several researchers have reported on the impact of disasters on hydropower facilities and their surrounding environments. These studies emphasize the necessity of post-disaster facility rehabilitation, taking into account factors such as geographical shifts, human displacement, and the replacement of turbines with suitable alternatives (Baidar et al. , 2016. Goda et al. , 2. Baidar et al conducted a study on the impact of the 7. 6 magnitude earthquake that struck the Gorkha district of Nepal, resulting over 8000 fatalities. It affected numerous large-scale hydropower plants and damaged hundreds of microhydropower plants, necessitating both short-term and long-term rehabilitation efforts. Their research concluded that majority of existing micro-hydropower plants employed Pelton a crossflow turbine, despite the suitability of Francis turbines for many of these locations. An initial assessment of 61 micro-hydropower revealed that over 50% of the sites were better suited to Francis's turbines. Consequently, the study proposes a strategic rehabilitation plan for the affected power plants, which includes replacing older turbines with francis turbines in suitable locations. Another challenge in hydropower facility management is the frequent underestimation of sedimentation during the planning of ancillary infrastructure (Cabral et al. , 2024. Sidle et al. , 2. Despite sufficient surface water availability, several water resource projects have failed to meet expected outcomes primarily due to sedimentation issues. For instance. Nepal's river basins are recognized as having some of the highest sediment yields globally, yet reliable data on actual sediment production remains scarce. A case in point is the Kulekhani Reservoir in Nepal, where sedimentation processes have been studied to identify appropriate sediment management options and ensure the reservoir's long-term sustainability (Cabral et al. , 2024. Sangroula, 2. Flood hazards have also impacted power plant operations. Damage from flooding is often attributed to inadequate forest planning and management. While the occurrence of floods is inherently difficult to predict and control, mitigation measures are necessary to reduce risks to human life and infrastructure (Amin et al. , 2022. Kuniyal et al. , 2. Decisive steps are required, such as the construction of dams, which provide various economic, environmental, and social benefits, including recreation, flood control, and water supply. Materials & Methods Data was collected through direct access to internal company documents as well as through an interview process with individuals who were direct witnesses to the 2018 earthquake. The data collected in this research includes various sources, including Investigation reports, reports regarding damage, and documents -other relevant documents. Then also analyze post-earthquake images that visualize the impact of the damage. The data collected was then confirmed with the results of interviews conducted with related parties who had direct involvement in the incident. Results and Discussion The Effects of Seismic Activity on Operational Performance Upon the occurrence of a seismic event, the mini-hydropower plant undergoes an automatic shutdown as precautionary measure. Due to the magnitude of the earthquake and the extent of the resulting damage, the system is subsequently subjected to a complete shutdown. The series of earthquakes that impacted Lombok Island in 2018 commenced on Juli 29th with a magnitude of 6. 4, followed by a magnitude of 6. 2 on August 5th, and culminated in two earthquakes occurring within a 10-hour interval on August 19th, registering magnitudes of 6. 5 and 6. 9, respectively. Figure 1. Power Production in July, 2018 The immediate impact of the earthquake on power production was a cessation of power generation due to damage to Journal of Renewable Energy. Electrical, and Computer Engineering, 5 . 37-44 the electricity distribution network infrastructure in the earthquake-affected area. The collapse of electricity poles, severance of distribution cables, and damage to electrical grid structures prompted the state electricity company (PLN) to halt the power supply, consequently leading to the shutdown of the power plant. Production records indicate that on July 29th, 2018, et approximately 8:00 AM local time, the generating unit underwent an emergency shutdown due to the earthquake and remained inoperative. The power plant was subsequently brought back to online on August 13th, 2018, at 2:00 PM (Figure . Figure 2. Power Production in August, 2018 Figure 2 also illustrates that, following the resumption of operations, the system continued to experience frequent disruptions, necessitating the shutdown of the power plant. These disruptions stemmed from disturbances within the electrical grid, primarily attributed to cable repairs, pole replacements, pole collapses, fallen trees, and other consequential events in the aftermath of the earthquake. In the instance of the seismic event on August 19th, the power plant was deactivated and rendered inoperable for a duration of 28 hours. At the onset of the earthquake, the hydropower plant was operating at a capacity of 1 MW. However, the seismic event forced a cessation of operations for a period of 366 hours. This resulted in production loss of 366 MWh. A subsequent aftershock on August 19th further disrupted plant operations, leading to a 28-hour downtime and an additional production loss of 28 MWh. Moreover, disruptions to the electricity grid during August caused an additional 33 hours of operational downtime, contributing to a further production loss of 33 MWh. In total, cumulative production losses attributed to the earthquake and grid disturbances throughout August reached 426 MWh. The repercussions of the earthquake persisted into September. An aftershock measuring 5. 3 on Richter scale on September 11th resulted in a 6-hour operational downtime. This, coupled with 33 hours of grid repairs, led to a total downtime of 39 hours for September. Consequently, the cumulative potential production loss reached 39 MWh. Overall, the cumulative production loss due to the earthquake reached 466 MWh. Comprehensive data regarding downtime during the earthquake can be found in Table 1. Month July August September Table 1. Downtime During the Earthquake Earthquake-induced Downtime due to grid downtime (Hour. maintenance (Hour. Total Potential losses (MW. Post-Earthquake Impact on Operational Earthquakes not only inflict immediate damage to hydropower plant infrastructure but also exert long-term effects on their operation. One significant consequence is the increased volume of sediment, rocks, and logging debris transported by water during the rainy season. Journal of Renewable Energy. Electrical, and Computer Engineering, 5 . 37-44 Figure 3. Image of the Channel During the Rainy Season (Documentation. January 23, 2. This disruption not only elevates the risk of sediment accumulation in the channel (Figure . but also leads to blockage of the hydropower plant intake by rocks and debris carried by the water flow. This accumulation of sediment and intake blockage directly contributes to increased operational downtime, necessitating more intensive and frequent maintenance to ensure the smooth flow of water and the continued operation of power plants. This situation necessitates continuous channel clearing to ensure unimpeded water flow to the turbines. Consequently, this alters the operators' work patterns, requiring them to conduct more frequent patrols and channel cleaning. Furthermore, the utilization of excavators to remove blockage materials adds to the operational costs of the hydropower These increases in operational costs and shifts in operator work patterns represent consequences of the earthquakeAos impact that must be borne by the plant. A significant sedimentation phenomenon occurred within the hydropower plant's catchment area following the This phenomenon commenced in November and December 2018, with a relatively low intensity. The intensity of sedimentation then escalated substantially from January to March 2019, before beginning to subside in early April 2019. This surge in sedimentation intensity is closely correlated with the rainy season in the region. High precipitation within the catchment area carries materials such as sediment, rocks, and logging debris into the rivers and streams leading to the hydropower plant. These materials subsequently accumulate in the channels and intake, leading to channel overfilling and blockage of the intake, ultimately preventing water from reaching the plant's turbine system. It was recorded that in the rainy month (January Ae Apri. in 2018 there was no downtime caused by sediment, but after the earthquake, namely in the rainy month of 2019, downtime was recorded for 142 hours in January, 154 hours in February, and decreased in March to 47 hours and April 25 hours as the rainy season ends, as seen in Table 4. Total downtime due to sediment in 2019 was 368 hours and in 2020 it increased to 1541 hours. Table 2. Downtime Due To Debris (Hour. January February March April Total This situation presents a challenge to the operational activities of the Kokok Putih hydropower plant. Continuous channel clearing efforts and regular monitoring of the catchment area are crucial for minimizing the negative impacts of sedimentation and maintaining smooth plant operation. However, during the subsequent rainy season, the volume of sediment and debris transported from upstream did not decrease but instead increased. Consequently, downtime escalated, reaching 373 hours in January 2020, 454 hours in February 2020, and 573 hours in March 2020, before finally decreasing to 141 hours in April 2020, coinciding with the end of the rainy season (Table . Post-Earthquake Impact on Electricity Generation The eastern region of Lombok Island typically experiences its rainy season from November to April, as illustrated in Figure 4, which presents rainfall data over a four-year period. The production pattern of the hydropower plant generally aligns with these distinct wet and dry seasons. The wet season, characterized by higher rainfall, occurs between November and April, while the dry season, with lower precipitation, prevails from May to October. Journal of Renewable Energy. Electrical, and Computer Engineering, 5 . 37-44 Figure 3. Rainfall Data for 2014,2017,2018, and 2019 (BPS East Lombo. This pattern is reflected in the hydropower plant's production graph (Figure . , where electricity generation peaks between February and March, coinciding with the high-rainfall period of the rainy season. During this period, the water flow to the turbines increases, resulting in greater energy production. Conversely, during the dry season, characterized by low rainfall, water discharge in the rivers and streams declines, leading to a decrease in the plant's electricity generation. This is evident in the graph, where electricity production reaches its lowest point in August and September. Figure 4. Electricity Production from 2016-2020 January February March April May June July August September October November December Table 3. Electricity Production from 2016-2020 . 1,102,608 1,194,560 1,014,160 628,880 2,011,968 1,309,120 1,146,480 699,600 1,798,992 2,298,640 1,634,560 851,600 1,110,960 2,169,360 1,571,920 1,040,560 912,888 1,216,480 956,240 1,292,080 730,800 927,920 788,400 1,042,880 767,808 776, 320 652,320 1,128,720 721,680 697,920 359,280 1,105,040 649,440 613,440 796,240 997,440 695,640 684,800 816,080 029,840 676,800 772,640 927,840 864,640 1,005,144 820,560 839,520 578,800 284,720 190,960 128,880 689,200 952,640 810,400 867,760 936,400 923,680 911,360 791,520 676,160 To examine the production changes before, during, and after the earthquake, the same data are presented in tabular form (Table . This tabular representation allows for a more precise quantitative analysis of post-seismic production By comparing the values within the table, insights into both the immediate and long-term impacts of the Journal of Renewable Energy. Electrical, and Computer Engineering, 5 . 37-44 earthquake on production activities can be obtained. Prior to the 2018 earthquake, the hydropower plant's production in 2016 and 2017 followed a seasonal pattern influenced by rainfall. Production exhibited a gradual increase from January to February or March, followed by a decline in April and May. This pattern can be attributed to the abundant water availability during the rainy season and the subsequent reduction in water flow during the dry season. Figure 4 illustrates that the hydropower plant's productivity in July and August 2018 was lower compared to previous This decline stemmed from a series of earthquakes in late July and August 2018, which induced downtime and consequently reduced productivity. Following the 2018 earthquake, the plant's production graph reveals a significant shift in the production pattern for 2019 and 2020. In contrast to the pre-earthquake pattern, where production consistently increased during the wet season, the post-earthquake period exhibits a decline in production during these wetter months. This is clearly evident in December 2018, where despite the onset of the rainy season, the hydropower plant experienced a decline in production compared to November. This phenomenon contrasts with the pre-earthquake pattern, in which December consistently exhibited higher production than November. To compare production changes during the rainy season before and after the earthquake. Table 4 was created, with the average monthly pre-earthquake production calculated as the mean production for the respective month from 2016, 2017, and 2018. The average pre-earthquake production data were then compared with the corresponding monthly production in 2019 and 2020, revealing the percentage decrease in production compared to the average pre-earthquake production. Table 4. Comparison of Monthly Production Before and After Earthquake During Rainy Season . Pra gempa Pasca gempa 2016 - 18 Tahun 2019 Tahun 2020 Production Production Reduction Production Reduction Average Month January 1,103,776 628,880 474,896 284,720 819,056 February 1,489,189 699,600 789,589 190,960 1,298,229 March 1,910,731 851,600 1,059,131 128,880 1,781,851 April 1,617,413 1,040,560 576,853 689,200 928,213 Total 6,121,109 3,220,640 2,900,469 1,293,760 4,827,349 Table 4 demonstrates that the downward trend in production persisted into the early months of the following year. January-March of 2019, the hydropower plantAos output exhibited figures significantly below those of previous years. For instance, production in January 2019 reached only 628,880 kWh, equivalent to 57% of the average January production from 2016 to 2018, indicating a 43% decrease. A similar phenomenon was observed in February and March 2018, as illustrated in Table 4. The subsequent rainy season in 2020 exhibited a more pronounced decline in production during the rainy months compared to 2019. This downward trend commenced in November 2019 and persisted into December 2019. Unlike 2019, where production showed a slight increase from January to March, production in 2020 steadily declined despite the increasing rainfall intensity in January. February and March. The lowest point in production occurred in March 2020, when the hydropower plant generated only 128,880 kWh . It represents 6. 7% of the average March production before the earthquake, significantly a substantial 93. 3% reduction in output. Aggregating the production for these four months to represent the decline in rainy season output, it can be concluded that in 2019, the rainy season production experienced a 47. 4% decrease, and in 2020, an even more substantial 78. decrease compared to the average rainy season production before the earthquake. This drastic decline highlights the longterm impact of the earthquake on the hydropower plantAos performance. The decline in electricity production during the rainy season at the Kokok Putih mini-hydro power plant exerts a dominant influence on the total annual output. This is evident in Figure 4, which illustrates that the rainy season constitutes the period of highest production, approaching the plantAos maximum installed capacity. Consequently, this reduction in rainy season production significantly impact the companyAos revenue, potentially affect the survival business viability. Mitigation measures implemented Damage to the catchment area has resulted in long-term disruptions to the hydropower plantAos operation, primarily through intake blockage and sediment accumulation in the water channels. Both of these factors contribute to reduced power generation due to decreased water flow to the turbines, sometimes even necessitating complete shutdown due to insufficient water supply. Therefore, implementing mitigation measures to address this issue is of most importance to restore and enhance the plantAos productivity. Direct mitigation within the catchment area is not programmed because the hydropower plantAos catchment area falls within the Gunung Rinjani National Park, a designated area managed exclusively by government-appointed agencies. Therefore, feasible mitigation measures do not aim to rehabilitate the catchment areas itself but rather to prevent the negative impacts of catchment area itself but rather to prevent the negative impacts of catchment degradation on the plantAos To address the production decline caused by frequent downtime resulting from intake blockage and sediment accumulation in the water channels, the following mitigation measures were implemented: constructing an additional Journal of Renewable Energy. Electrical, and Computer Engineering, 5 . 37-44 intake as an alternative when the existing intake is blocked. increasing the number of excavators to expedite sediment removal from the channels. and constructing a second channel from the new intake to the settling basin, parallel to the existing channel, as an additional solution to mitigate downtime caused by sediment accumulation. Year Table 5. Mitigation Measures for Catchment Area Degradation Mitigation Purpose Reducing downtime attributed to Constructing an additional intake intake obstruction Adding an excavator and constructing a secondary channel to the settling basin Mitigating downtime caused by sediment accumulation in Results of mitigation measures To analyze the changes before and after the implementation of mitigation measures. Table 6. Was complied, presenting downtime data attributed to sedimentation during the rainy season months from 2020 to 2023. This data representation facilitates a more precise quantitative analysis of fluctuations in debris-related disruption following the mitigation efforts. January February March April Total Table 6. Operational Disruptions Due To Debris (Hour. A decline of 87% A decline of 96% A decline of 98% relative to the 2020 relative to the 2021 relative to the 2021 The initial mitigation measure, implemented in 2020, involved the construction of an additional intake. The positive impact of this supplementary intake is evident in the reduction of debris-related downtime, as illustrated in table 6. During the 2020 rainy season, downtime reached 1541 hours. However, following the addition of the new intake, it decreased substantially to 207 hours in 2021, representing an 87% reduction- a considerable achievement. This reduction in downtime is caused by reduced occurrences of blockages at the intake. Previously, blockages in tunnel-shaped intakes by materials such as large stones and forest waste wood often caused the unit to shutdown completely because there was no water flow to the channel. Overcoming this problem takes quite a long time, especially due to access difficulties and work safety considerations during bad weather. With additional intake, the risk of blockage can be minimized, thereby reducing down time by up to 87%. Then in Table 6. We can also see the effect of mitigation measures taken in 2021 in the form of increasing the number of excavators and building a second channel from the intake to the settling tank. These two steps were able to reduce the downtime figure from 188 hours in 2021 to 8 hours in 2022 and 3 hours in 2023. A fairly large achievement is a reduction in downtime of above 96%. Conclusions The 2018 Lombok earthquake severely impacted the Kokok Putih hydropower plant, highlighting a critical oversight in post-disaster recovery: while physical damage was addressed, operational disruptions from landslides in the catchment area were neglected. This led to a significant decline in productivity, unmitigated until 2020 when strategic measures, including a new intake, additional excavators, and a secondary channel, were implemented, successfully restoring preearthquake production levels. This experience underscores the need for comprehensive risk assessment and proactive mitigation in post-disaster recovery to ensure the resilience of hydropower plants. Acknowledgments The authors wish to express sincere gratitude to the Directorate of Research. Technology, and Community Service. Directorate General of Higher Education. Research and Technology. Ministry of Education. Culture. Research and Technology, for their financial support through the postgraduate grant program. Furthermore, the authors acknowledge with gratitude the assistance to PT Nusantara Indo Energi, the operator of the Kokok Putih mini-hydro power plant, in granting access and facilitating data collection. References