ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. Utilization of BIM for Construction Cost Estimation of the Girder Bridge Structure in the IKN Project (Karang JoangAeKKT Kariangau Segmen. Irna Hendriyani1. Reno Pratiwi1. Risa Aghix Primastyo Utomo1 1Departement of Civil Engineering. Balikpapan University AAirna. hendriyani@uniba-bpn. The implementation of Building Information Modeling (BIM) is increasingly important for improving the efficiency and accuracy of quantity takeoff and cost estimation in large-scale infrastructure projects. This study evaluates 5D BIM using Allplan Engineering for girder bridge structural work . ilecap, pier, and pierhea. in the IKN Toll Road project. Karang JoangAeKKT Kariangau Segment, and compares the results with Quantity Surveyor (QS) data and manual recalculation based on Detailed Engineering Design (DED) drawings. Using a comparative quantitative approach, the study developed a 3D model from DED data and performed BIM-based quantity extraction and cost estimation using unit prices from the project Budget Plan (RAB). The results show close agreement across methods, with total differences below 1% for both reinforcement and concrete quantities and costs. Compared with QS. BIM results are 0. 17% lower for reinforcement and 17% higher for concrete. compared with manual recalculation, differences range from approximately 17% to 0. Item-level discrepancies are most evident in Pierhead PH1 . p to 2. 72% for concret. and Pier P1 . p to 3. 02% for reinforcemen. Overall, 5D BIM in Allplan Engineering provides reliable and traceable outputs for quantity takeoff and cost estimation and supports faster updates during design revisions in national-scale infrastructure projects. Keywords: Building Information Modeling (BIM). 5D BIM. Allplan Engineering. quantity takeoff (QTO). girder bridge. IKN Toll Road. Submitted: November 26, 2025 Revised: December 5, 2025 Accepted: December 18, 2025 Published: December 20, 2025 Introduction Technology in the construction sector offers significant benefits across various aspects of work, including modeling, planning, cost and volume estimation, sustainable development, and facility management (Prastya. Celvin Adi Prastya. Hendriyani. Irna. Pratiwi Reno, 2. Currently, many companies have integrated automation through software, notably through the implementation of Building Information Modeling (BIM). BIM is a 3D modeling technology capable of representing all information within a construction project, including methods, materials, management, and work sequences. The implementation of BIM consists of several stages, commonly referred to as dimensions, which represent the level of execution relative to the construction phases. These dimensions include 3D . isualization and collaboratio. , 4D . , 5D . ost estimation and volume takeof. , 6D . , and 7D . acility managemen. To support the BIM concept, specialized software is required, such as Allplan Engineering. This software can be utilized to design construction models in 3D for structural, architectural, and Mechanical. Electrical, and Plumbing (MEP) works. Through 3D modeling, 2D working drawings and cost estimation analyses for each construction component can be generated. While previous BIM studies (Suasira. I Wayan. Tapayasa. I Made. Santiana. I Made Anom. Wibawa. I Gede Satra, 2. and (Diantoro. Bayu Rahmad. Hendriyani. Irna. Pratiwi. Reno, 2. utilized Tekla and Autodesk Revit, this study conducts a BIM analysis using Allplan Engineering. Among the seven BIM dimensions, cost estimation planning is critical in construction planning. 5D BIM serves as an alternative solution to achieve the necessary precision. High accuracy in construction cost estimation is essential for achieving planning efficiency. Research by Farhana and Abma (Farhana. Amalina. Abma. Vendie, 2. indicates that using the 5D BIM concept for cost estimation results in a deviation of approximately A7% or less compared to the initial Budget Plan (RAB). This approach is particularly relevant for the development of IndonesiaAos New Capital (IKN) currently underway in East Kalimantan. One of the ongoing projects is the IKN Toll Road 3A. Karang Joang Ae KKT Kariangau Segment, located in North Balikpapan. The contract value for this project is IDR 3,335,421,077,000. ncluding 11% VAT). The project comprises several structures, including a 9. 94 km main road, 2,975 m of slabon-pile, a 415 m girder bridge, five overpasses, and one How to cite this article: Hendriyani I. Pratiwi R. Utomo R. Utilization of BIM for Construction Cost Estimation of the Girder Bridge Structure in the IKN Project (Karang JoangAeKKT Kariangau Segmen. Buletin Profesi Insinyur, 8. , 84Ae93. This is an open access article under the CC BY-NC-SA license BPI, 2025 | 84 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. This study focuses on the structural work of Girder Bridge 1, which includes sub-items such as foundations . ile cap. , columns . , floor slabs, girders, bore piles, abutments, and barriers, with an estimated structural concrete cost of IDR 47,081,022,901. In construction project management, three primary aspects must be prioritized: time efficiency, cost control and cost minimization, and quality standards compliance (Salsabila & Abma, 2. In practice, cost estimation for bridge projects faces various technical and managerial Conventional estimation methods still rely on the interpretation of 2D drawings and manual calculations by planning consultants. This situation is prone to human error, information duplication, and discrepancies between the design model and field conditions. Furthermore, design changes during execution often necessitate major revisions to the Budget Plan (RAB), leading to delays and cost The lack of integration between technical disciplinesAisuch as structural, architectural, and MEPAi often causes overlapping work volumes or material specification mismatches. Based on this background, this research implements the 5D BIM concept using Allplan Engineering software to evaluate the output of BIM-based cost estimation . D BIM) in supporting structural work cost estimation. The analysis provides a comparison between BIM-based cost estimation and manual recalculation based on design drawings. It is expected that this study will enhance the effectiveness and efficiency of Girder Bridge construction in the IKN Toll Road project. Karang Joang Ae KKT Kariangau Segment. The research questions for this study are formulated as follows: . how is the volume analysis and cost estimation conducted using the Building Information Modeling (BIM) concept for the Girder Bridge construction in the IKN Project. Karang Joang Ae KKT Kariangau Segment? . what is the variance in volume and cost analysis between the BIM method and the manual recalculation method for the Girder Bridge construction in the IKN Project. Karang Joang Ae KKT Kariangau Segment? The objectives of this research are . to analyze the volume and cost estimation using the Building Information Modeling (BIM) concept for the structural work of the Girder Bridge in the IKN Project. Karang Joang Ae KKT Kariangau Segment. to analyze the variance in volume and cost between the BIM method and the manual recalculation method for the Girder Bridge construction in the IKN Project. Karang Joang Ae KKT Kariangau Segment. Research Methodology This study was conducted to evaluate the implementation of the Building Information Modeling (BIM) concept using Allplan Engineering software in supporting the preparation of the Budget Plan (RAB) for construction projects. The methods employed in this research include a literature study, data collection. BIM-based modeling, and cost estimation analysis . D BIM). Literature Study This stage aims to identify theories, concepts, and previous research findings relevant to BIM implementation for volume takeoff and cost estimation in infrastructure The analyzed sources include scientific articles. ISSN 2654-5926 research reports, and Allplan Engineering software manuals. Primary references are derived from prior studies, including Suasira et al. Diantoro et al. , and Prastya et al. , which explored the effectiveness of BIM in construction cost estimation. Based on the literature findings, the study framework and data requirements were determined to support the modeling and cost estimation Data Collection The data collected pertains to the IKN Toll Road Project. Karang Joang Ae KKT Kariangau Segment. North Balikpapan. East Kalimantan. The data consist of the structural work Budget Plan (RAB) and the Detailed Engineering Design (DED). Additionally, supporting information such as technical specifications and unit price analysis (Analisa Harga Satuan Pekerjaan/AHSP) based on actual project documents was gathered. These data serve as the primary inputs for BIM modeling and subsequent volume and cost Modeling and BIM-Based Cost Estimation . D BIM) Based on the DED and technical drawings, the bridge structure was remodeled using Allplan Engineering 2021. The modeling process followed architectural and structural templates in accordance with technical standards for reinforced concrete structures. This process produced a 3D model integrated with material quantity data . oncrete and reinforcement volume. , which was subsequently used to generate BIM-based cost estimation outputs using the 5D BIM approach. The outputs from this stage provide BIMbased quantities and cost estimates to be evaluated against conventional estimation methods. Volume and Cost Estimation Analysis (Compariso. The BIM-based volume and cost estimation results were compared with the Quantity Surveyor (QS) analysis and manual recalculation based on design drawings. The QS analysis refers to data processed by the projectAos QS team. This comparison was conducted to assess the variance in volume and cost between methods and to evaluate the accuracy of BIM-based estimation relative to QS and manual Comparative Analysis and Data Validation The calculation results from the three methods (BIM. QS, and manual recalculatio. were analyzed using a comparative approach. Differences among methods were calculated as percentage deviations for both reinforcement and concrete volumes, as well as the resulting cost Validation was conducted to ensure that the BIMbased quantities and cost outputs remained consistent with the DED, technical specifications, and other project documentation, andAiwhere applicableAifield conditions. Results Interpretation and BIM Efficiency Evaluation The final stage involves interpreting the results to evaluate the efficiency and accuracy of BIM implementation in cost The evaluation focuses on the benefits of BIM in terms of time effectiveness, quantity precision, and the ease of revising the Budget Plan (RAB) when design changes BPI, 2025 | 85 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. The research was conducted at the IKN Toll Road Project. Karang Joang Ae KKT Kariangau Segment. North Balikpapan District. Balikpapan City. East Kalimantan Province. The geographical location is illustrated in Figure 1. Table 2 Recapitula on of Reinforcement Quan ty for Girder Bridge Structure Based on QS Analysis No. Work Item Volume Pilecap P1. P2. P3. P4 21,410. Pier 1 23,897. Pier 2 36,587. Pier 3 35,741. Pier 4 37,592. Pierhead 1 68,679. Pierhead 2, 3, 4 172,817. Total 396,726. Figure 1 Project loca on Results Project Information This study evaluates 5D BIM implementation for quantity takeoff and cost estimation in the IKN Toll Road project. Karang Joang Ae KKT Kariangau Segment, located in Balikpapan City. East Kalimantan. The analysis focuses on the girder bridge structural work . ilecap, pier, and pierhea. using three approaches: QS data. BIM outputs from Allplan Engineering, and manual recalculation based on DED drawings. Quantity Takeoff Results QS-Based Quantities QS quantities were obtained from official project For example, the concrete volume for Pier P1 reported in QS records is 69. 12 mA (Figure . The QS recapitulation of concrete volumes for pilecap, pier, and pierhead work is presented in Table 1, with a total concrete volume of 3,816. 13 mA. The QS recapitulation of reinforcement quantities is presented in Table 2, with a total reinforcement quantity of 396,726. 31 kg (Figure 3 provides an example of the reinforcement record from project Table 1 Concrete Volumes for Pilecap. Pier, and Pierhead Works (QS Dat. No. Work Item Unit Volume Pilecap P1. P2. P3. P4 2,183. Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 1,033. Total 3,816. Figure 2 Pier 1 concrete volume data from the QS (Project Document Sourc. Manual Recalculation Quantities Manual recalculation was conducted using DED drawings following the conventional consultant approach. The recapitulation of concrete volume from recalculation is presented in Table 3, with a total of 3,816. 13 mA for the evaluated work items. The recapitulation of reinforcement quantity from recalculation is shown in Table 4, yielding a total reinforcement quantity of 395,816. 98 kg. BIM-Based Quantities (Allplan Engineerin. The bridge structure was remodeled using Allplan Engineering, and quantities were extracted from the BIM The concrete volume recapitulation is shown in Figure 4, while reinforcement quantity recapitulation is shown in Figure 5. Cost Estimation Results (Basis: Budget Plan/RAB) Cost estimation in this study used unit prices from the projectAos Budget Plan (RAB) applicable to the Karang Joang Ae KKT Kariangau Segment (Figure . Using identical unit prices across methods ensures that cost differences arise from quantity differences only. BPI, 2025 | 86 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. QS Cost Estimation The QS-based cost recapitulation for bridge girder structure work is presented in Table 5. The total cost is IDR 21,289,228,148. 64, consisting of IDR 13,088,533,545. 00 for concrete work and IDR 8,200,694,603. 64 for reinforcement BIM Cost Estimation (Allplan Engineerin. The BIM-based cost estimation results are presented in Table 6. The total cost is IDR 21,297,158,541. 80, consisting of IDR 13,110,314,615. 00 for concrete work and IDR 8,186,843,926. 80 for reinforcement work. Table 4 Calcula on of reinforcement volume for bridge girder structure work based on recalcula on No. Work Item Unit Volume Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 Total 21,472. 23,915. 36,600. 35,630. 37,608. 68,441. 172,148. 395,816. Figure 4 Concrete Volume Recapitula on (Allplan Engineering Sourc. Figure 3 . Pilecap reinforcement quan ty record (Project Document Sourc. Table 3 Recapitula on of concrete volume of bridge girder structure work based on recalcula on No. Work Item Unit Volume Pilecap P1. P2. P3. P4 2,183. Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 1,033. Total 3,816. Figure 5 Recapitula on of reinforcement volume (Allplan Engineering Sourc. DAFTAR KUANTITAS DAN HARGA SATKER PAKET PROVINSI : SATUAN KERJA PELAKSANAAN JEMBATAN PULAU BALANG : JALAN TOL IKN SEGMEN KARANGJOANG - KKT KARIANGAU : KALIMANTAN TIMUR No. Mata Pembayaran Item Pekerjaan Manual Recalculation Cost Estimation The manual recalculation cost results are presented in Table The total cost is IDR 21,256,372,259. 28, consisting of IDR 13,088,293,060. 00 for concrete work and IDR 8,168,079,199. 28 for reinforcement work. DIVISI 7. STRUKTUR Beton struktur, fc '30 MPa Baja Tulangan Sirip BjTS 420B Satuan Harga Satuan (R. 3,435,500. 20,636. Figure 6 Unit Price List for Girder Bridge Work (Project Document Sourc. BPI, 2025 | 87 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. Table 5 Recapitula on of bridge girder structure work costs Unit Price (IDR) QS (Quantity Surveyo. Total Price Amount (IDR) No. Item Details Unit Concrete Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. Sub Total 2,183. 1,033. 7,502,754,095. 237,461,760. 329,808,000. 318,814,400. 340,801,600. 808,888,475. 3,550,005,215. 13,088,533,545. Reinforcement Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 20,636. 20,636. 20,636. 20,636. 20,636. 20,636. 20,636. Sub Total Total 21,551. 23,197. 36,711. 35,989. 37,556. 68,441. 173,949. 444,744,389. 478,694,117. 757,584,911. 742,675,401. 775,024,394. 1,412,355,698. 3,589,615,691. 8,200,694,603. 21,289,228,148. Volume (Quan ty Surveyor Data Sourc. Table 6 Recapitula on of bridge girder structure work costs with Allplan Engineering BIM (Builiding Information Modelin. Total Price Volume Amount (IDR) No. Item Details Unit Unit Price (IDR) Concrete Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. Sub Total 2,183. 1,033. 7,502,754,095. 237,461,760. 329,808,000. 318,814,400. 340,801,600. 830,910,030. 3,549,764,730. 13,110,314,615. Reinforcement Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 20,636. 20,636. 20,636. 20,636. 20,636. 20,636. 20,636. Sub Total Total 21,410. 23,897. 36,587. 35,741. 37,592. 68,679. 172,817. 441,828,935. 493,139,317. 755,021,300. 737,562,625. 775,760,274. 1,417,272,225. 3,566,259,247. 8,186,843,926. 21,297,158,541. (Allplan Engineering Source 2. Comparative Results Reinforcement Quantity Comparison The reinforcement quantity comparison across QS. BIM, and manual recalculation is summarized in Table 8 and visualized in Figure 7. The total reinforcement quantity based on BIM is 396,726. 30 kg, which is 0. 17% lower than the QS total . ,397. 49 k. Compared with manual recalculation . ,816. 98 k. , the BIM total is 0. 23% higher. Item-level deviations of BIM relative to QS range from Oe0. 66% to 02%, while deviations relative to manual recalculation range from Oe0. 29% to 0. Concrete Quantity Comparison Table 9 shows that the total concrete volume for the bridge girder structure using the QS analysis is 3,809. 79 mA, while the BIM analysis is 3,816. 13 mA, or 6. 34 mA higher than the QS analysis. The deviation from the BIM method relative to the QS analysis ranges from Oe0. 01% to 2. Meanwhile, the total concrete volume using the recalculation method is 3,809. 72 mA, or 0. 17% lower than the BIM analysis. The deviation relative to the recalculation method ranges from 0 to 2. Graphically, the total concrete volume for the three methods is shown in Figure 8. BPI, 2025 | 88 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. Table 7 Recapitula on of bridge girder structure work costs with recalcula on Recapitulation No. Item Details Unit Unit Price (IDR) Concrete Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. 3,435,500. Sub Total 2,183. 1,033. 7,502,754,095. 237,461,760. 329,808,000. 318,814,400. 340,801,600. 808,888,475. 3,549,764,730. 13,088,293,060. Reinforcement Pilecap P1. P2. P3. P4 Pier 1 Pier 2 Pier 3 Pier 4 Pierhead 1 Pierhead 2, 3, 4 20,636. 20,636. 20,636. 20,636. 20,636. 20,636. 20,636. Sub Total Total 21,472. 23,915. 36,600. 35,630. 37,608. 68,441. 172,148. 443,098,049. 493,513,448. 755,294,727. 735,262,330. 776,093,958. 1,412,355,698. 3,552,460,985. 8,168,079,199. 21,256,372,259. Volume Total Price (IDR) Amount Table 8 Recapitula on of reinforcement analysis on bridge girder structure work Reinforcement Volume . Work Item Pilecap PH 1 PH 2 Amount BIM Recalculation BIM VS QS 21,551. 23,197. 36,711. 35,989. 37,556. 68,441. 173,949. 397,397. 21,410. 23,897. 36,587. 35,741. 37,592. 68,679. 172,817. 396,726. 21,472. 23,915. 36,600. 35,630. 37,608. 68,441. 172,148. 395,816. -1,131. Difference % BIM BIM VS VS QS Recalculation % BIM VS Recalculation Reinforcement Volume 397,500. 397,000. 396,500. 396,000. 395,500. 395,000. BIM Recalculation Analysis Method Figure 7 Reinforcement Volume Comparison Chart BPI, 2025 | 89 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. Table 9 Recapitula on of concrete volume analysis on bridge girder structure work Concrete Volume . Work Item BIM Pilecap PH 1 PH 2 Amount 2,183. 1,033. 3,809. 2,183. 1,033. 3,816. Recalculation BIM VS QS 2,183. 1,033. 3,809. Difference BIM VS % BIM VS QS Recalculation % BIM VS Recalculation Concrete Volume . 3,820. 3,815. 3,810. 3,805. BIM Recalculation Analysis Method Figure 8 Concrete Volume Calcula on Summary Reinforcement Cost Comparison Reinforcement cost comparison is summarized in Table 10 and visualized in Figure 9. BIM yields a reinforcement cost of IDR 8,186,843,926. 80, which is 0. 17% lower than QS (IDR 8,200,694,603. Compared with manual recalculation (IDR 8,168,079,199. BIM is 0. 23% higher. Deviations follow the reinforcement quantity patterns. Concrete Cost Comparison Concrete cost comparison is summarized in Table 11 and visualized in Figure 10. BIM yields a concrete cost of IDR 13,110,314,615. 00, which is 0. 17% higher than QS (IDR 13,088,533,545. Compared with manual recalculation (IDR 13,088,293,060. BIM is also 0. 17% higher. Key Findings BIM-based quantities and cost estimates generated using Allplan Engineering are highly consistent with QS documentation and manual recalculation. At the total level, differences remain below 1% for both reinforcement and concrete quantities and for the resulting costs under the same RAB unit price basis. The largest item-level differences are concentrated in Pierhead PH1 for concrete quantities and Pier P1 for reinforcement quantities. Table 10 Analysis of the cost of reinforcing bridge girder structure work Reinforcement Price (IDR) Work Item Pilecap PH 1 PH 2 Jumlah BIM Recalculation BIM VS QS 444,744,389. 478,694,117. 757,584,911. 742,675,401. 775,024,394. 1,412,355,698. 3,589,615,691. 8,200,694,603. 441,828,935. 493,139,317. 755,021,300. 737,562,625. 775,760,274. 1,417,272,225. 3,566,259,247. 8,186,843,926. 443,098,049. 493,513,448. 755,294,727. 735,262,330. 776,093. 1,412,355,698. 3,552,460,985. 8,168,079,199. -2,915,454. 14,445,200. -2,563,610. -5,112,775. 735,879. 4,916,527. -23,356,443. -13,850,676. Difference % BIM BIM VS VS QS Recalculation -1,269,114. -374,130. -273,427. 2,300,294. -333,684. 4,916,527. 65 13,798,261. 17 18,764,727. % BIM VS Recalculation BPI, 2025 | 90 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. Reinforcement price (IDR) 8,220,000,000 8,200,000,000 8,180,000,000 8,160,000,000 8,140,000,000 BIM Recalculation Analysis Method Figure 9 Recapitula on of Reinforcement Costs for Girder 1 Bridge Work Table 11 Concrete cost analysis of bridge girder structure work Concrete Price (IDR) Work Item BIM Recalculation BIM VS QS Pilecap PH 1 PH 2 Jumlah 7,502,754,095. 237,461,760. 329,808,000. 318,814,400. 340,801,600. 808,888,475. 3,550,005,215. 13,088,533,545. 7,502,754,095. 237,461,760. 329,808,000. 318,814,400. 340,801,600. 830,910,030. 3,549,764,730. 13,110,314,615. 7,502,754,095. 237,461,760. 329,808,000. 318,814,400. 340,801,600. 808,888,475. 3,549,764,730. 13,088,293,060. 22,021,555. -240,485. 21,781,070. Difference % BIM BIM VS VS QS Recalculation 72 22,021,555. 17 22,021,555. % BIM VS Recalculation Concrete price (IDR) 13,120,000,000 13,100,000,000 13,080,000,000 13,060,000,000 BIM Recalculation Analysis method Figure 10 Concrete cost analysis diagram for bridge girder structure work BPI, 2025 | 91 ISSN 2654-5926 Buletin Profesi Insinyur 8. 084Ae093 http://dx. org/10. 20527/bpi. Discussion Agreement with Prior 5D BIM Studies The small total variance (<1%) between BIM outputs and conventional methods supports prior evidence that 5D BIM can produce acceptable cost estimation accuracy. Farhana and Abma . reported that 5D BIM may achieve deviations within approximately A7% compared to conventional estimation. the present study demonstrates a tighter agreement for the evaluated work scope and documentation basis. Interpreting Item-Level Deviations Although totals are consistent, item-level deviations are not uniform. The largest deviation in concrete quantities occurs at Pierhead PH1, indicating that pierhead geometry may be more sensitive to modeling interpretation . , segmentation of concrete components, rounding conventions, or differences between drawing-based measurement and model object For reinforcement, the highest deviation appears at Pier P1, which may reflect differences in reinforcement detailing interpretation or categorization between QS records and BIM extraction. This aligns with Suasira et al. , emphasizing that BIM QTO accuracy depends on consistent modeling practices and sufficient level of detail. Practical Benefits: Revision Speed and Data Integration Beyond numerical accuracy, 5D BIM provides workflow Chan. Olawumi, and Alfred . highlight that 5D BIM links geometric models with cost databases, enabling automatic cost updates when the model This capability reduces repeated manual recalculation, improves traceability, and supports faster decision-making during design revisionsAiparticularly relevant for large infrastructure projects. Comparison with Studies Reporting Larger Variance Compared with studies reporting larger discrepancies . Setiawan et al. , 2025, with reinforcement and concrete volume variances up to 13. 53% and 10. 22%), the present results indicate that controlled scope, clear DED inputs, and consistent RAB unit price basis can contribute to strong agreement among BIM. QS, and manual recalculation. Lifecycle Implications BIM can also support downstream phases by storing geometry and material information in a unified database. As noted by Katke . , this supports operation and maintenance by enabling easier access to asset Therefore, the BIM model developed for the girder bridge case may provide benefits beyond planning, provided that updates are maintained consistently. Conclusion The conclusions of this study are as follows: The results of the volume analysis for the girder bridge structural work . ilecap, pier, and pierhea. using the BIM concept show a reinforcement quantity of 396,726. 30 kg and a concrete volume of 3,816. 13 mA. The estimated reinforcement cost is IDR 8,186,843,926. 80, while the estimated concrete cost is IDR 13,110,314,615. Compared with the QS analysis, the difference in reinforcement quantity obtained using the BIM concept is 671. 19 kg . ith a cost difference of IDR 13,850,676. , indicating that BIM is 0. 17% lower than QS for reinforcement. For concrete work, the BIM result differs from QS by 6. 34 mA . ith a cost difference of IDR 21,781,070. , indicating that BIM 17% higher than QS for concrete. When compared with manual recalculation, the BIM results also show small differences, indicating that the BIM-based estimates are consistent with conventional calculations. Overall, the total variance between BIM. QS, and manual recalculation remains below 1% for both quantities and costs under the same unit price basis from the project Budget Plan (RAB). These findings indicate that 5D BIM using Allplan Engineering can reliably support quantity takeoff and cost estimation for bridge structural work while providing practical advantages in updating quantities and revising the Budget Plan (RAB) when design changes occur. Acknowledgement The authors would like to express their gratitude to PT Hutama Karya. PT Adhi Karya, and PT Brantas Abipraya for facilitating access to project data and providing access to Allplan Engineering software to support this research. Reference